The bridge is a longitudinal glued-laminated timber deck bridge using southern pine lumber. It is 17 ft long by 7 ft wide. The bridge was designed for an 85 psf uniform live load with a reduced deflection limitation of L/240. There are four deck panels placed side by side. Each Combination 48 deck panel is 21 inches wide by 5 inches thick. All wood components were preservative treated with pentachlorophenol to 0.6 lb/cu. ft. retention levels. In addition, components in contact with soil were given surface applications of copper naphthanate.
Faculty, Students, and Staff that helped with construction were:
Dr. Steve Taylor, Dr. Jim Baier, Doc Flynn, Matt Veal, Andrew Boutwell, Jon Davis, Eric Phillips, and Lori Montgomery.